Skip to main content
Practice Guide for Audit of Contract Management
-
The practice guide issued by cag on audit of contract management is
mandatory in nature.
-
True
-
False
-
The supplementary series of guidelines issued by cag, for conducting p
a is facilitative in nature.
-
True
-
False
-
Audit objectives in contract mangement is to look out for
-
Whether there exists a system in the organization for project
appraisal
-
Whether there exists a system in the organization for project
appraisal which is effectively functional,
-
No such system is available,
-
Such system is available but ineffective.
-
The project appraisal system provides for consultation with
-
No outside bodies
-
Disciplines such as finance, technical, planning and legal,
-
Disciplines such as finance, technical, planning and legal and
outside bodies
-
None of the above.
-
The need for appraisal of project is verified by
-
Persons who are in relation to the need
-
Other persons who are not in relation to the need,
-
Both (A) and (B),
-
Neither (A) and (B).
-
An approved list of contractors will be made by admitting them in the
list by
-
Giving notice/advt in local newspapers,
-
Giving notice/advt in local newspapers with time limit
-
No such notice/advt is required,
-
None of the above.
-
The financial appraisals of contractors include
-
Examination of Finance a/cs of the co. for last 2 years
-
Examination of Finance a/cs of the co. for last 2 years which are
published
-
Examination of Finance a/cs of the co. for last 3 years which are
published
-
Examination of Finance a/cs of the co. for last 3 years
-
The appraisal of list of contractors will include
-
No such appraisals
-
Financial appraisals
-
Financial and Technical appraisals
-
Legal, Financial and Technical appraisals.
-
Technical appraisals include,
-
Particulars of recent contracts completed by contractor including
their value and nature,
-
Particulars of recent contracts completed by contractor,
-
Particulars of recent contracts completed by contractor including
contracts which are still in progress,
-
None of the above.
-
The proper selection of contractors is by
-
Open Tender
-
Competitive
-
Selective, restrictive and negotiated
-
All the above.
-
An exemption procedure of selection of contractor in an emergency and
single source of supply does exist in a Company.
-
True
-
False
-
Final selection of a contractor is based on
-
Technical appraisal by authorized authority
-
Financial appraisal by authorized authority
-
Both (A) and (B)
-
None.
-
All tender envelopes/forms received by the organization should be
endorsed by authorized staff,
-
With date
-
With date and time
-
Just endorsement
-
Not required.
-
Tender envelopes can be denied acceptance due to late submission
-
True
-
False
-
All tender envelopes with the authorized officers can be opened by
officers who have initiated tender process.
-
True
-
False
-
Tender envelopes can be opened in the presence of at least 2 officers
from different disciplines other than officers who have initiated such
process.
-
True
-
False
-
Any modifications of tender conditions/review of conditions are
permissible subsequent to initiation of tender process, before closing
tender process.
-
True
-
False
-
Any Bond/Performance Bond(Surety) is to be received by the organization
any time before closing time of receipt of Tender document.
-
True
-
False
-
Under Stage B –Currency of Contract, Engineers have to send Project
Report.
-
True
-
False
-
A project Controller officially sends Contract Report.
-
True
-
False
-
A contract report is sent by
-
Contractor
-
Legal consultant
-
Engineer
-
Project controller
-
A contract report includes among other things,
-
Contractual claims which are accepted
-
Contractual claims which are not accepted
-
Contractual claims which are accepted & value ascertained
-
Contractual claims which are accepted and value not
ascertained.
-
A project report by the engineer shall report expenditure to date and
expected final cost compared with original estimated cost of the
project.
-
True
-
False
-
Quantities shown in the statement by the contractor should be supported
by on site measurement records.
-
True
-
False
-
Retention of sum, can be effected by the organization, without any
mention in the terms & conditions of contract.
-
True
-
False
-
Inclusion of elements and proportions of work attributable to price
indices shall form part of tender document.
-
True
-
False
-
Any variations in work can be issued by persons who are not authorised
so, under the contract.
-
True
-
False
-
Engineer has to inform the organization on a daily basis of the net
effect of variations on cost of works.
-
True
-
False
-
Day work sheets endorsed to identify the variation to which they refer
are signed by engineer’s representative and are sent to organization
with supporting documents at each monthly valuation.
-
True
-
False
-
Any claim for a rate higher than one notified by the engineer which is
properly substantiated by the engineer is permissible.
-
True
-
False
-
Under stage-c final contract, all measured items of work need to be
re-measured on completion and are supported by site measurements
record.
-
True
-
False
-
In determining final amount payable it is necessary for the authority
to make allowances for previous payments under same item of expenditure,
tax matters, deletion of prime cost items, provisional sums and
contingency items not used.
-
True
-
False
-
Liquidated damages should not be recovered from the contractor, which
represent ‘genuine pre-estimate of loss’.
-
True
-
False
-
Payment of liquidated damages shall also carry interest.
-
True
-
False
-
On termination of contract, state of work assessed may or may not
include value of work done by the contractor up to forfeiture, estimated
cost of remedial work at current rates and estimated cost of unfinished
work as per contract.
-
True
-
False
-
All extra cost involved due to incompletion of work by contractor, on
termination of contract, need not be recovered from defaulting
contractor
-
True
-
False